The Washington County Highway Department will be pulverizing and repaving a 1.5-mile stretch of County Trunk Highway S, from State Trunk Highway 28 north to the Fond du Lac County line in the Village and Town of Kewaskum. The project is anticipated to begin the week of July 13, 2026, with substantial completion anticipated by August 14, 2026, dependent on weather and other factors.
The road will be closed to through traffic but residents will be able to get to and from their homes or businesses as needed.
The intersection of County Trunk Highway S and State Trunk Highway 28 will not be reconstructed as part of this project, and will be open to east and west traffic on State Highway 28.
A detour route will not be posted.
Curb repairs, manhole and inlet adjustments, new asphalt surface, shouldering, sightline improvements, striping, and signs are all included. Stark Asphalt is the prime contractor.
Project information was released by the Washington County Highway Department, as they continue to improve and maintain Washington County’s roadways.